A Look Ahead (2)
Posted Tue, 09/01/2009 - 12:50 by mattacker
The framing is getting wrapped up. They still have to install the windows, and build the screen porch and other "punch list" items. But as you can see, the structure is built. Here is what's next:
-It's time for the subs to "rough it in." The HVAC, plumber, and electrician are going to commence the rough work. This should ake about 1.5 to 2 weeks, and ends with the inspector saying we are good to cover up the walls.
-In this time frame, we will pour the garage floor.
-The insulator will insulate spots that will be covered by tubs.
-We are also going to have our 1st meeting with Laura Paprocki to consult on energy conservation matters. I'll go into detail on this after the meeting.